* 15199 (T) |
Chart: 6212 |
Sweden. Northern Baltic. Norrköping. Inner harbour. Norra kajen. Reconstruction works of quays. |
|
Time: August 31, 2020 - Autumn 2022 Reconstruction work will be carried out in the area shown in the chartlet. The quay line will be moved out up to approx. 9 m in connection with the area being adapted to housing. Sheet piling work is planned to be carried out 31 August - 25 September in area a) and 21 September - 23 October in area b) according to the chartlet. Work is carried out from land and from smaller pontoons in the harbor basin. |
58-35,69N | 016-12,01E | Inner harbour, Norra Kajen |
Not shown in ENC. |
Norrköping Inner harbour. Norra hamnen. Reconstruction works |